Conference article

Risk Assessment of River-Type Hydropower Plants by Using Fuzzy Logic Approach

S. Kucukali
Cankaya University, Department of Civil Engineering, Ankara, Turkey

Download articlehttp://dx.doi.org/10.3384/ecp110571432

Published in: World Renewable Energy Congress - Sweden; 8-13 May; 2011; Linköping; Sweden

Linköping Electronic Conference Proceedings 57:8, p. 1432-1439

Show more +

Published: 2011-11-03

ISBN: 978-91-7393-070-3

ISSN: 1650-3686 (print), 1650-3740 (online)

Abstract

In this paper; a fuzzy rating tool has been developed for river-type hydropower plant projects risk assessment and expert judgments have been used instead of probabilistic reasoning. The methodology is a multi-criteria decision analysis which provides a flexible and easily understood way to analyze project risks. The external risks; which are partly under the control of companies; have been considered in the model. The eleven classes of risk factors were determined based on the expert interviews; field studies and literature review as follows: site geology; land use; environmental issues; grid connection; social acceptance; financial; natural hazards; political/regulatory changes; terrorism; access to infrastructure and revenue. The relative importance (impact) of risk factors was determined from the survey results. The survey was conducted with the experts that have experience in river-type hydropower projects. The survey results revealed that the site geology and environmental issues were considered as the most important risks. The new risk assessment method enabled a Risk Index (R) value to be calculated; establishing a 4-grade evaluation system: low risk having R values between 1.2 and 1.6; medium risk; between 1.6 and 2; high risk; between 2 and 2.4; extreme risk; between 2.4 and 2.8. Applicability of the proposed methodology was tested on a real case hydropower project namely Kulp IV which was constructed on Dicle River in East Anatolia in Turkey. The proposed risk analysis will give investors a more rational basis on which to make decisions and it can prevent cost and schedule overruns.

Keywords

Hydropower; Risk Analysis; Fuzzy Logic

References

[1] Gronbrekk; W.; Barton; H.; and Khoury; R.H.; International sustainability tools for hydropower role; relevance and industry reporting trends. Proc.; Hydro 2010 Conf.; Lisbon; Portugal; 2010.

[2] Komendantova; N.; Patt; A.; Barras; K. and Battaglini; A.; Perception of risks in renewable energy projects: The case of concentrated solar power in North Africa; Energy Policy; 2011; In press.

[3] Ernst and Young; Business Risk Report; 2010. (www.maplecroft.com )

[4] Zavadskas; E.K.; Turskis; Z.; Tamosaitiene; J.; Risk assessment of construction projects; J. Civil Engineering and Management; 16; 2010; 33-46 doi: 10.3846/jcem.2010.03.

[5] Dikmen; I.; Birgonul; M.T.; Han; S.; Using fuzzy risk assessment to rate cost overrun risk in international construction projects; Int J Project Management; 25; 2007; 494-505. doi: 10.1016/j.ijproman.2006.12.002.

[6] Kangari; R. and Riggs; L.S.; Construction risk assessment by linguistics; IEEE Transactions on Engineering Management; 36; 1989; 126-131. doi: 10.1109/17.18829.

[7] Mustafa; M.A.; and Al-Bahar; J.F.; Project risk assessment using the analytic hierarchy process; IEEE Transactions on Engineering Management; 38; 1991; 46-52. doi: 10.1109/17.65759.

[8] Kucukali; S.; Baris; K.; Turkey’s short-term gross electricity demand forecast by fuzzy logic approach; Energy Policy; 38(5); 2010; 2438-2445. doi: 10.1016/j.enpol.2009.12.037.

[9] ECR-Euro Money Country Risk; 2010. (www.euromoney.com)

[10] Maplecroft ; Terrorism Risk Index; 2010. (www.maplecroft.com )

[11] Karakaya; S.T.; Coastal Scenic Evaluation by Application of Fuzzy Logic Mathematics; Msc. Thesis; METU;The Graduate School of Natural and Applied Sciences; Dept.of Civil Eng.; Ankara; Turkey; 2004.

[12] Sahin; F.; Scenic Evaluation of the Western Black Sea Coasts Using Fuzzy Logic; Msc. Thesis; ZKU; Graduate Sc. Of Natural and App. Sci.; Dept. of Civil Eng.; Zonguldak; Turkey; 2008 (inTurkish).

[13] Boyle; G.; Renewable Energy: Power for a Sustainable Future. Oxford University Press; 2004.

[14] Kucukali; S. and Baris; K.; Assessment of small hydropower (SHP) development in Turkey: Laws; regulations and EU policy perspective; Energy Policy; 37; 2009; 3872-3879. doi: 10.1016/j.enpol.2009.06.023.

[15] Hall; D.G.; Hunt; R.T.; Reeves; K.S. and Carroll; G.R.; Estimation of Economic Parameters of U.S. Hydropower Resources; Idaho National Engineering and Environmental Laboratory; 2003.

[16] Gordon; J.L.; Hydropower costs estimates; J Water Power Dam Constr; 35; 1983; 30-37.

[17] Gordon; J.L. and Noel; C.R.; The economic limits of small and low-head hydro; J Water Power Dam Constr; 38; 1986; 23-26.

[18] Aggidis; G.A.; Luchinskaya; E.; Rothschhild; R. and Howard; D.C.; The costs of small-scale hydropower production: Impact on the development of existing potential; Renewable Energy; 35; 2010; 2632-2638. doi: 10.1016/j.renene.2010.04.008.

Citations in Crossref